Public Safety Training Center

Proposed Bond Project Information

Project Budget: $10,400,000

Bond Issuance Date: September 2022
Project Start Date: May 2022
Construction Start Date: November 2022
Estimated Completion Date: December 2023
Architect: Moseley Architects
Construction Manager-At-Risk: Samet Corportation
Operating Impact: $136,965

Public Safety Training Center

Public Safety Center:
• 15,000 SF with 24 lanes
• Six Classrooms adjoining Indoor Firing Range and Fire Tower
• Dedicated Shooting Simulator Space
• Basic Law Enforcement Training
• Driving Pad
• Emergency Medical Services (Future)

Public Safety Training Center
Bond Project Updates

Click on the description to see information regarding bond project progress.

On May 10th, the Green Level Planning Board approved recommendation for conditional use. The request for conditional use will be considered by the Green Level Town Council on June 9th. Once approved, the College can begin the process of fence construction around the parcels. In addition, geotechnical activities will be completed on the training parcel needed for the civil engineering design work. The design team is close to completing the schematic design of the project and will now have a third-party construction estimator provide cost estimates for the project. The College will also have Samet complete a construction estimate as well. Alamance Community College expects to bid the project in November with construction commencing in late December/early January.